Customer-Owned (Parallel) Generation - Michigan

The following information will guide you through the steps and requirements necessary to interconnect a parallel system to the WPS electric distribution system.

PLEASE NOTE: PDF files require Acrobat Reader 5.0 or greater. If you don't have this version, you can download your free copy from Adobe.

For Systems 20kW or Less

  1. Start the Interconnection Process
     
    Contact Kevin Pitts at Wisconsin Public Service to review your project:
    Phone: 920-433-4964
    E-mail: klpitts@wisconsinpublicservice.com
  2. Review and Understand the Rates, Rules and Requirements
  3. Complete Interconnection Application
     
    Complete and submit the Michigan Generator Interconnection Application, with the applicable review fee, to:
     
    Attn: Kevin Pitts
    Wisconsin Public Service
    P.O. Box 19007
    Green Bay, WI 54307-9007
  4. Application Review
     
    Your application will be reviewed by WPS to determine if it contains all of the information required to begin the interconnection process. You will then be notified by WPS regarding the status of your application. If the application is incomplete, additional information will be requested.
  5. Determine if Distribution Study is Needed
     
    After your application is considered complete, WPS will determine if a distribution study is needed. This study is to assess the level of impact your system will have once connected to our grid.
     
    If the study is required, you will be notified with the cost of that study. Upon written authorization to proceed, and payment of the applicable fee, we will complete the distribution study.
  6. Discuss Distribution Study and Review Interconnection Options & Costs
     
    Once the study is complete, WPS will contact you to discuss all of the options available — along with their associated costs — and the project timeline for the interconnection of your parallel generation system.
  7. Installation of parallel generation and Distribution System Upgrades
     
    You will need to install your generating equipment within a mutually agreed upon timeframe. After receipt of payment for the agreed-upon interconnection costs, we will perform all work needed to upgrade our distribution system to accommodate your parallel generation system.
  8. System Testing
     
    When the installation of your system is complete, WPS must be notified and given the opportunity to witness or verify the system testing. This could include:
    • Witnessing commissioning tests;
    • Performing anti-islanding tests; or
    • Verifying the protective equipment settings
  9. Interconnection Agreement
     
    Before parallel operation can begin, a Generator Interconnection and Operating Agreement will need to be completed and signed by the applicant and Wisconsin Public Service.

Back to Top

For Systems Greater than 20kW

  1. Start the Interconnection Process
     
    Contact Bruce Hahn at Wisconsin Public Service to review your project:
    Phone: 920-433-1461
    E-mail: bhhahn@wisconsinpublicservice.com
  2. Review and Understand the Rules & Requirements
  3. Select Parallel Generation Rate Preference
  4. Review Requirements and Complete Interconnection Application and Agreement
     
    Based on the size of your parallel generation project, review the Michigan Generator Interconnection Requirements. Then, complete the included Interconnection Application and Interconnection and Operating Agreement.
     

    Submit the completed Interconnection Application and Interconnection and Operating Agreement, with the applicable review fee, to:
     
    Attn: Bruce Hahn
    Wisconsin Public Service
    P.O. Box 19007
    Green Bay, WI 54307-9007
  5. Application Review
     
    Your application will be reviewed by WPS to determine if it contains all of the information required to begin the interconnection process. You will then be notified by WPS regarding the status of your application. If the application is incomplete, additional information will be requested.
  6. Determine if Distribution Study is Needed
     
    After your application is considered complete, WPS will determine if a distribution study is needed. This study is to assess the level of impact your system will have once connected to our grid.
     
    If the study is required, you will be notified with the cost of that study. Upon written authorization to proceed, and payment of the applicable fee, we will complete the distribution study.
  7. Discuss Distribution Study and Review Interconnection Options & Costs
     
    Once the study is complete, WPS will contact you to discuss all of the options available — along with their associated costs — and the project timeline for the interconnection of your parallel generation system.
  8. Installation of parallel generation and Distribution System Upgrades
     
    You will need to install your generating equipment within a mutually agreed upon timeframe. After receipt of payment for the agreed-upon interconnection costs, we will perform all work needed to upgrade our distribution system to accommodate your parallel generation system.
  9. System Testing
     
    When the installation of your system is complete, WPS must be notified and given the opportunity to witness or verify the system testing. This could include:
    • Witnessing commissioning tests;
    • Performing anti-islanding tests; or
    • Verifying the protective equipment settings

Back to Top